Oman

Omani certificates are I-RECs from a handful of large, new solar plants. The state power buyer, Nama PWP, registers the plants it contracts and auctions their certificates. Supply is far larger than what is used.

Updated 17 October 2026

CertificateI-REC(E), listed by RE100 as not yet in common use
IssuerThree Pillars Consulting, a local issuer. First issue June 2022
I-RECs issued7.1 million MWh to September 2026, of which 1.73 million in January to September 2026
I-RECs redeemed for users in Oman0.07 million MWh in 2025, and 0.23 million MWh from January to September 2026
Main sellerNama Power and Water Procurement, the state single buyer of power, by auction and direct agreement
Market boundaryOman. Certificates must come from Omani plants
Grid4.5% renewable in 2025, according to Ember, almost all solar. Gas makes up 92%

Supply

Four active plants issue Omani I-RECs, all solar and together 1,816 MW. The issuer's 2026 country report names them: Ibri II (560 MW), Manah I and Manah II (528 and 623 MW, commissioned in 2024 and 2025), and Amin (105 MW). A 50 MW wind farm in Dhofar and a small rooftop system are registered but listed as inactive.

Omani I-REC issuance by year, million MWh
2022
0.32
2023
0.70
2024
2.75
2025
1.59
2026, Jan to Sep
1.73

Source: Xpansiv I-REC Registry, by date of issue, which can include generation from earlier years. 2026 covers nine months only.

Much more supply than use

Between June 2025 and September 2026, 3.27 million Omani I-RECs were issued but only about 0.25 million were redeemed, and nearly all of those for users in Oman. The rest are held, or have been sold but not yet used. Nama PWP says it has sold more than 600,000 certificates to buyers in Oman and is offering around 3 million; each Manah plant can produce about 1.5 million a year.

For a buyer, this means local supply is unlikely to be the constraint. The certificates are also young: all 2026 issuance comes from plants built since 2020, well inside RE100's 15-year window.

Who sells the certificates

Oman has no national certificate scheme or green tariff. Instead the state single buyer, Nama Power and Water Procurement (Nama PWP), registers renewable plants in its contracted portfolio with I-REC and sells their certificates. Its first auction, for the Dhofar wind farm, was announced in early 2024. It offered over 3 million certificates from Manah I, Manah II and Dhofar in its fourth round in July 2025. It also sells through direct agreements of a year or longer. Bidders register through Nama PWP's supplier portal.

Other plants sell their own. Ibri II is registered by its project company, and Amin by its owner, which offers its certificates for sale. The issuer's report says most registrants sell directly to companies, without a marketplace or broker.

One plant, two buyers

Amin sells all its electricity to Petroleum Development Oman under a contract to 2043, but its certificates are offered to anyone. Whoever holds and redeems the I-RECs makes the renewable claim; the electricity buyer should not also claim that output. We did not find the clause on certificates in any Omani power contract. Ask the seller which plant the certificates come from and who buys its power.

Buying electricity directly

Since April 2026, a framework from the regulator, the Authority for Public Services Regulation, lets licensed renewable producers sell directly to qualified customers and use the grid to deliver it, within an annual quota. The largest band, above 50 MW per customer, is reserved at first for a "National Champion Company"; projects below 0.25 MW are reserved for small local firms. We read press accounts of the decision, not the text, and they do not mention certificates. For most buyers, I-RECs or on-site solar remain the practical routes.

RE100 and Scope 2

Oman is its own market: RE100 recognises no Gulf-wide single market. Omani I-RECs redeemed for users in Bahrain or Qatar, under 1% of redemptions since June 2025, do not meet RE100's market boundary. Seeimported certificates.

RE100 lists Oman among markets where certificates exist but are not yet in common use. There, cancelling certificates is not required unless certificates were issued for the generation being claimed, but RE100 recommends using them as best practice.

Before you buy

  • Ask for the plant name and generation period, and who buys the plant's electricity.
  • Make sure the redemption names your Omani legal entity and gives Oman as the location of consumption. See redemption statements.
  • If you buy at a Nama PWP auction, check which plants and generation months are on offer.
I-RECs issued and redeemed per quarter, to Q3 2026
  • Issued from plants here
  • Redeemed for users here
012202220242026Issued from plants here, Q1 2020: 0.00 million MWhIssued from plants here, Q2 2020: 0.00 million MWhIssued from plants here, Q3 2020: 0.00 million MWhIssued from plants here, Q4 2020: 0.00 million MWhIssued from plants here, Q1 2021: 0.00 million MWhIssued from plants here, Q2 2021: 0.00 million MWhIssued from plants here, Q3 2021: 0.00 million MWhIssued from plants here, Q4 2021: 0.00 million MWhIssued from plants here, Q1 2022: 0.00 million MWhIssued from plants here, Q2 2022: 0.21 million MWhIssued from plants here, Q3 2022: 0.12 million MWhIssued from plants here, Q4 2022: 0.00 million MWhIssued from plants here, Q1 2023: 0.23 million MWhIssued from plants here, Q2 2023: 0.23 million MWhIssued from plants here, Q3 2023: 0.06 million MWhIssued from plants here, Q4 2023: 0.18 million MWhIssued from plants here, Q1 2024: 1.61 million MWhIssued from plants here, Q2 2024: 0.07 million MWhIssued from plants here, Q3 2024: 0.14 million MWhIssued from plants here, Q4 2024: 0.93 million MWhIssued from plants here, Q1 2025: 0.02 million MWhIssued from plants here, Q2 2025: 0.03 million MWhIssued from plants here, Q3 2025: 1.47 million MWhIssued from plants here, Q4 2025: 0.07 million MWhIssued from plants here, Q1 2026: 0.84 million MWhIssued from plants here, Q2 2026: 0.01 million MWhIssued from plants here, Q3 2026: 0.89 million MWhRedeemed for users here, Q1 2020: 0.00 million MWhRedeemed for users here, Q2 2020: 0.00 million MWhRedeemed for users here, Q3 2020: 0.00 million MWhRedeemed for users here, Q4 2020: 0.00 million MWhRedeemed for users here, Q1 2021: 0.00 million MWhRedeemed for users here, Q2 2021: 0.00 million MWhRedeemed for users here, Q3 2021: 0.00 million MWhRedeemed for users here, Q4 2021: 0.00 million MWhRedeemed for users here, Q1 2022: 0.00 million MWhRedeemed for users here, Q2 2022: 0.00 million MWhRedeemed for users here, Q3 2022: 0.00 million MWhRedeemed for users here, Q4 2022: 0.00 million MWhRedeemed for users here, Q1 2023: 0.02 million MWhRedeemed for users here, Q2 2023: 0.00 million MWhRedeemed for users here, Q3 2023: 0.00 million MWhRedeemed for users here, Q4 2023: 0.01 million MWhRedeemed for users here, Q1 2024: 0.01 million MWhRedeemed for users here, Q2 2024: 0.00 million MWhRedeemed for users here, Q3 2024: 0.00 million MWhRedeemed for users here, Q4 2024: 0.01 million MWhRedeemed for users here, Q1 2025: 0.06 million MWhRedeemed for users here, Q2 2025: 0.00 million MWhRedeemed for users here, Q3 2025: 0.01 million MWhRedeemed for users here, Q4 2025: 0.00 million MWhRedeemed for users here, Q1 2026: 0.21 million MWhRedeemed for users here, Q2 2026: 0.01 million MWhRedeemed for users here, Q3 2026: 0.02 million MWh

million MWh

Source: Xpansiv I-REC Registry, I-REC(E) only, our quarterly totals. Issued counts plants in this country; redeemed counts certificates claimed for users here, wherever the plant is.

Show data
PeriodIssued from plants hereRedeemed for users here
Q1 20200.000.00
Q2 20200.000.00
Q3 20200.000.00
Q4 20200.000.00
Q1 20210.000.00
Q2 20210.000.00
Q3 20210.000.00
Q4 20210.000.00
Q1 20220.000.00
Q2 20220.210.00
Q3 20220.120.00
Q4 20220.000.00
Q1 20230.230.02
Q2 20230.230.00
Q3 20230.060.00
Q4 20230.180.01
Q1 20241.610.01
Q2 20240.070.00
Q3 20240.140.00
Q4 20240.930.01
Q1 20250.020.06
Q2 20250.030.00
Q3 20251.470.01
Q4 20250.070.00
Q1 20260.840.21
Q2 20260.010.01
Q3 20260.890.02

Download quarterly volumes for all 43 countries (CSV)

Sources

  1. Xpansiv I-REC Registry: aggregated monthly statistics, data to September 2026 (XLSX, via I-TRACK Foundation)
  2. I-TRACK Foundation: Oman country page
  3. Three Pillars Consulting for I-TRACK: Country Assessment Report, Oman, version 2.0 (April 2026)
  4. Nama Power and Water Procurement: 7-Year Statement 2025-2031, issue 19
  5. Nama Power and Water Procurement: auctions
  6. Oman Observer: Oman widens renewable certificate market (12 October 2026)
  7. OQ: Amin solar project registration with I-REC (18 September 2022)
  8. MEED: Oman opens door to direct power sales (4 August 2026)
  9. RE100 technical criteria and appendices (March 2025)
  10. Ember: yearly electricity data (full release, CSV)