| Certificate | I-REC(E), the instrument in common use according to RE100 |
| Local issuer | Normex, since 2022 |
| Registry | Evident (Xpansiv) |
| I-REC country since | 2017 |
| Issued in 2025 | 10.8 million MWh, about 4% of I-RECs issued worldwide |
| Issued January to September 2026 | 10.6 million MWh |
| Market boundary | Mexico. Certificates must come from Mexican plants |
| Grid | About 74% fossil in 2025, according to Ember |
What counts in Mexico
I-RECs are the instrument companies use for voluntary claims. RE100 lists I-REC as the system in common use in Mexico, so its members must cancel certificates to claim renewable electricity from the grid.
I-RECs and CELs
Mexico's Clean Energy Certificates (CELs) are a compliance instrument. Large consumers must cover a share of their consumption with them, set at 13.9% for both 2025 and 2026. Since the Electricity Sector Law of March 2025, CELs are issued by the National Energy Commission. RE100 lists CELs as a Mexican system that is not in common use for voluntary claims.
The two systems are kept apart so the same megawatt-hour is not counted twice. Plants commissioned before August 2014 are not eligible for CELs and can issue I-RECs freely. Since November 2022, newer plants must first show that they have voluntarily cancelled the same volume of CELs before they receive I-RECs.
We have not found an official statement on whether this cancellation procedure changed when the National Energy Commission replaced the Energy Regulatory Commission in 2025. Ask your supplier how the plant behind your certificates was cleared.
Supply
- Wind
- 72.4%
- Solar
- 12.4%
- Hydro
- 7.7%
- Bioenergy
- 6.4%
- Geothermal
- 1.1%
Source: Xpansiv I-REC Registry. Shares of 10.6 million MWh issued.
- 2020
- 1.8
- 2021
- 2.3
- 2022
- 7.2
- 2023
- 7.6
- 2024
- 11.1
- 2025
- 10.8
- 2026, Jan to Sep
- 10.6
Source: Xpansiv I-REC Registry, by date of issue. 2026 covers nine months only.
Almost all Mexican I-RECs are used in Mexico: 99.6% of those redeemed since June 2025 named a beneficiary there. Redemptions peak in February and March, as companies close the previous year's reporting.
The plant-age question
RE100 requires at least 85% of a member's renewable electricity to come from plants commissioned or repowered in the last 15 years. For a 2026 claim, that means 1 January 2011 or later.
- Before 2005
- 2.7%
- 2005–2014
- 57.5%
- 2015–2019
- 26.3%
- 2020–2024
- 12.9%
- 2025 onward
- 0.6%
Source: Xpansiv I-REC Registry.
More than half of current supply comes from wind farms built between 2005 and 2014. Part of that group is already older than RE100's window, and the rest will age out over the next few years. Supply that meets the rule increasingly comes from plants built after 2014, which must clear the CEL cancellation step first. Specify the commissioning year when you ask for a quote.
Imported certificates
Since June 2025, 12% of the I-RECs redeemed for beneficiaries in Mexico were issued abroad, mostly inGuatemala. RE100 treats Mexico as its own market, so these do not support an RE100 claim for Mexican consumption, even though the two grids are connected. Seeimported certificates.
Before you buy
- Ask for the plant, technology and commissioning date.
- Check the certificates were issued in Mexico.
- If the plant was commissioned after August 2014, ask for confirmation that the matching CELs were cancelled.
- Match the vintage to your reporting year.