| Certificate | I-REC(E), also sold locally as mREC. RE100 lists I-REC and TIGR as in common use |
| Issuer | The Green Certificate Company, the central issuer. I-TRACK expects a national issuer to be appointed during 2026 |
| I-RECs issued in 2025 | 11.5 million MWh |
| I-RECs redeemed for users in Malaysia, 2025 | 8.9 million MWh |
| Market boundary | Malaysia. Certificates must come from Malaysian plants |
| Grid | 21% renewable in 2025, according to Ember, mostly hydro. Coal and gas make up the rest |
An mREC is an I-REC
You will see Malaysian certificates called mRECs. I-TRACK describes mREC as a local name for I-RECs, and TNBX, the TNB subsidiary that runs the mGATS marketplace, uses it as a brand for the certificates it redeems. There is no separate national certificate.
Ways to buy
| Route | Who it suits | What you get |
|---|---|---|
| Green Electricity Tariff (GET) from TNB | TNB customers in Peninsular Malaysia. Non-residential blocks of 1 MWh, for one to three years | A premium on your bill. TNBX redeems certificates in your name once a year, within 45 working days of the year-end bill |
| mGATS marketplace and auctions, run by TNBX | Companies that want certificates without changing their tariff | Certificates redeemed directly to you. They can only be retired to Malaysian-resident buyers and cannot be resold |
| CRESS | High- and medium-voltage customers in Peninsular Malaysia contracting with a plant of at least 30 MW | Supply over the grid from a specific plant. Certificates pass to you by contract |
| Unbundled I-RECs from a registry participant | Any company, including sites outside the peninsula | Certificates redeemed in your name for the volume you choose |
TNB's GET terms allow the certificates to come from any renewable technology and from different plants, at TNB's discretion. If your customer or framework has requirements on technology or plant age, a direct purchase lets you specify them.
Supply
- Hydro
- 69.1%
- Solar
- 25.8%
- Bioenergy
- 5.1%
Source: Xpansiv I-REC Registry. Shares of 10.5 million MWh issued.
- 2021
- 1.3
- 2022
- 2.7
- 2023
- 14.7
- 2024
- 10.6
- 2025
- 11.5
- 2026, Jan to Sep
- 10.5
Source: Xpansiv I-REC Registry, by date of issue. 2026 covers nine months only.
Most Malaysian certificates are used at home: 94.7% of those redeemed since June 2025 named a beneficiary in Malaysia, and 5.2% in Singapore. Redemptions peak in February.
The plant-age catch
RE100 requires at least 85% of a member's renewable electricity to come from plants commissioned or repowered in the last 15 years. For a 2026 claim, that means plants commissioned on or after 1 January 2011.
- Before 2005
- 7.2%
- 2005–2014
- 60.3%
- 2015–2019
- 12.1%
- 2020–2024
- 17.8%
- 2025 onward
- 2.6%
Source: Xpansiv I-REC Registry.
Six in ten current certificates come from plants commissioned between 2005 and 2014. Those built before 2011 already fall outside RE100's window, and the rest of that group drops out by the 2030 reporting year. If your claim must meet RE100, specify the commissioning year when you ask for a quote.
Regulation to watch
- Third-party access. CRESS, in force since September 2024 and last revised in December 2025, lets large users buy renewable electricity from a developer over TNB's grid. Certificates must be redeemed in Malaysia.
- Exports to Singapore. Malaysia has approved cross-border sales of renewable electricity to Singapore through the Energy Exchange Malaysia (ENEGEM).
- Mandatory cancellation for RE100. RE100 lists Malaysia among markets where certificates are in common use, so from the 2027 CDP cycle its members must cancel certificates to claim grid electricity there.
Before you buy
- Ask for the plant, technology and commissioning date.
- If you already subscribe to the Green Electricity Tariff, do not buy separate certificates for the same consumption.
- Make sure the redemption names your Malaysian legal entity and gives Malaysia as the location of consumption. See redemption statements.