REC.marketGet notified

Markets · Indonesia

Indonesia

Most Indonesian certificates are sold by PLN, the state utility, and they are not I-RECs: PLN uses the TIGR registry. I-RECs exist too, and RE100 accepts either.

Updated 15 October 2026

CertificatesREC PLN, on the TIGR registry, and I-REC(E). RE100 lists I-REC as in common use and TIGR as not in common use, and does not require a particular system
Main sellerPLN, the state utility and single buyer of grid power
REC PLN sold in 20256.4 million MWh, according to PLN
I-RECs issued in 20253.6 million MWh, by the Green Certificate Company as central issuer
Market boundaryIndonesia. Certificates must come from Indonesian plants
GridCoal 62% in 2024, renewables 18%, according to Ember

REC PLN or I-REC

REC PLNI-REC
RegistryTIGR (APX, part of Xpansiv)Evident (Xpansiv)
SellerPLN only, from 12 of its own geothermal, hydro and solar plantsPlant owners and registry participants
How to buyOnline at layanan.pln.co.id. Retail purchases from 10 MWh; enterprise purchases from 200 MWh through PLN, for legal entitiesFrom a registry participant, which redeems in your name
DeliveryPLN retires the certificates in your name and emails the certificate within 14 working days of paymentRedemption statement from the registry
RestrictionsCannot be resold; claims limited to consumption in IndonesiaMust cover consumption in Indonesia

PLN also offers a "Dedicated Source" contract tied to specific plants, for larger multi-year volumes. Since July 2025 the commodity exchange ICDX has run trading in renewable energy certificates.

Who owns independent producers' attributes

In 2022 PLN said that only it may issue certificates for plants connected to its grid, including those of independent producers. I-TRACK briefly paused I-REC issuance for 20 such producers that year, and lifted the pause after no Indonesian authority responded. A 2025 energy ministry regulation says ownership of the attributes follows the law or the power purchase agreement. If you buy I-RECs from a plant that sells its power to PLN, ask the seller to confirm it holds the attribute rights.

Supply

Indonesian I-REC issuance by year, million MWh
2021
0.4
2022
1.5
2023
1.8
2024
1.8
2025
3.6
2026, Jan to Sep
3.3

Source: Xpansiv I-REC Registry, I-REC(E) only, by date of issue. 2026 covers nine months only. REC PLN is not included.

Indonesian I-REC issuance by technology, January to September 2026
Hydro
51.6%
Geothermal
33.2%
Bioenergy
7.7%
Solar
7.5%

Source: Xpansiv I-REC Registry. Shares of 3.3 million MWh issued.

About 75% of this year's I-RECs come from plants built since 2015, soRE100's plant-age rule is manageable. For REC PLN, ask which plants supply your certificates and when they were commissioned.

Regulation to watch

  • Power wheeling. The new and renewable energy bill, which would let companies buy renewable power from third parties over PLN's grid, had not passed as of September 2026.
  • PLN's 2025–2034 plan adds 69.5 GW of capacity, 42.6 GW of it renewable, which should increase certificate supply.
  • Mandatory cancellation for RE100. RE100 lists Indonesia among markets where certificates are in common use, so from the 2027 CDP cycle its members must cancel certificates to claim grid electricity there.

Before you buy

  • Ask for the plant, technology and commissioning date, whichever system you use.
  • For I-RECs from independent producers, confirm the seller holds the attribute rights.
  • Make sure the retirement names your Indonesian legal entity and gives Indonesia as the location of consumption. See redemption statements.
I-RECs issued and redeemed per quarter, to Q3 2026
  • Issued from plants here
  • Redeemed for users here
0122020202220242026Issued from plants here, Q1 2019: 0.01 million MWhIssued from plants here, Q2 2019: 0.11 million MWhIssued from plants here, Q3 2019: 0.04 million MWhIssued from plants here, Q4 2019: 0.25 million MWhIssued from plants here, Q1 2020: 0.12 million MWhIssued from plants here, Q2 2020: 0.03 million MWhIssued from plants here, Q3 2020: 0.01 million MWhIssued from plants here, Q4 2020: 0.24 million MWhIssued from plants here, Q1 2021: 0.10 million MWhIssued from plants here, Q2 2021: 0.06 million MWhIssued from plants here, Q3 2021: 0.04 million MWhIssued from plants here, Q4 2021: 0.16 million MWhIssued from plants here, Q1 2022: 0.57 million MWhIssued from plants here, Q2 2022: 0.03 million MWhIssued from plants here, Q3 2022: 0.40 million MWhIssued from plants here, Q4 2022: 0.50 million MWhIssued from plants here, Q1 2023: 0.45 million MWhIssued from plants here, Q2 2023: 0.22 million MWhIssued from plants here, Q3 2023: 0.57 million MWhIssued from plants here, Q4 2023: 0.53 million MWhIssued from plants here, Q1 2024: 0.42 million MWhIssued from plants here, Q2 2024: 0.26 million MWhIssued from plants here, Q3 2024: 0.55 million MWhIssued from plants here, Q4 2024: 0.54 million MWhIssued from plants here, Q1 2025: 0.84 million MWhIssued from plants here, Q2 2025: 0.63 million MWhIssued from plants here, Q3 2025: 1.12 million MWhIssued from plants here, Q4 2025: 0.98 million MWhIssued from plants here, Q1 2026: 1.31 million MWhIssued from plants here, Q2 2026: 1.00 million MWhIssued from plants here, Q3 2026: 0.94 million MWhRedeemed for users here, Q1 2019: 0.01 million MWhRedeemed for users here, Q2 2019: 0.01 million MWhRedeemed for users here, Q3 2019: 0.07 million MWhRedeemed for users here, Q4 2019: 0.04 million MWhRedeemed for users here, Q1 2020: 0.06 million MWhRedeemed for users here, Q2 2020: 0.01 million MWhRedeemed for users here, Q3 2020: 0.22 million MWhRedeemed for users here, Q4 2020: 0.05 million MWhRedeemed for users here, Q1 2021: 0.10 million MWhRedeemed for users here, Q2 2021: 0.16 million MWhRedeemed for users here, Q3 2021: 0.04 million MWhRedeemed for users here, Q4 2021: 0.07 million MWhRedeemed for users here, Q1 2022: 0.21 million MWhRedeemed for users here, Q2 2022: 0.10 million MWhRedeemed for users here, Q3 2022: 0.23 million MWhRedeemed for users here, Q4 2022: 0.08 million MWhRedeemed for users here, Q1 2023: 0.47 million MWhRedeemed for users here, Q2 2023: 0.36 million MWhRedeemed for users here, Q3 2023: 0.13 million MWhRedeemed for users here, Q4 2023: 0.36 million MWhRedeemed for users here, Q1 2024: 0.56 million MWhRedeemed for users here, Q2 2024: 0.58 million MWhRedeemed for users here, Q3 2024: 0.22 million MWhRedeemed for users here, Q4 2024: 0.47 million MWhRedeemed for users here, Q1 2025: 0.78 million MWhRedeemed for users here, Q2 2025: 0.28 million MWhRedeemed for users here, Q3 2025: 0.45 million MWhRedeemed for users here, Q4 2025: 0.78 million MWhRedeemed for users here, Q1 2026: 0.97 million MWhRedeemed for users here, Q2 2026: 1.02 million MWhRedeemed for users here, Q3 2026: 0.54 million MWh

million MWh

Source: Xpansiv I-REC Registry, I-REC(E) only, our quarterly totals. Issued counts plants in this country; redeemed counts certificates claimed for users here, wherever the plant is.

Show data
PeriodIssued from plants hereRedeemed for users here
Q1 20190.010.01
Q2 20190.110.01
Q3 20190.040.07
Q4 20190.250.04
Q1 20200.120.06
Q2 20200.030.01
Q3 20200.010.22
Q4 20200.240.05
Q1 20210.100.10
Q2 20210.060.16
Q3 20210.040.04
Q4 20210.160.07
Q1 20220.570.21
Q2 20220.030.10
Q3 20220.400.23
Q4 20220.500.08
Q1 20230.450.47
Q2 20230.220.36
Q3 20230.570.13
Q4 20230.530.36
Q1 20240.420.56
Q2 20240.260.58
Q3 20240.550.22
Q4 20240.540.47
Q1 20250.840.78
Q2 20250.630.28
Q3 20251.120.45
Q4 20250.980.78
Q1 20261.310.97
Q2 20261.001.02
Q3 20260.940.54

Download quarterly volumes for all 43 countries (CSV)

Sources

  1. Xpansiv I-REC Registry: aggregated monthly statistics, data to September 2026 (XLSX, via I-TRACK Foundation)
  2. I-TRACK Foundation: Indonesia country page
  3. I-TRACK Foundation: lifting the pause in issuance, Indonesia
  4. PLN: Renewable Energy Certificate
  5. PLN: REC categories
  6. PLN: GEAS terms and conditions
  7. PLN: REC users up 117 percent (press release, January 2025)
  8. PLN: REC sales (press release, January 2026)
  9. ICDX: initial trade for the renewable energy certificate auction
  10. RE100 technical criteria and appendices (March 2025)
  11. Ember: Indonesia electricity data