Certificates change your Scope 2 number only under the market-based method. Here is how the two methods differ, the rules a certificate must meet, and what is under revision.

Updated 15 October 2026

Two methods, both reported

Location-basedMarket-based
ReflectsThe average emissions of the grids where you use electricityThe emissions of the electricity you chose to buy, or your lack of choice
Emission factorGrid average for the locationFrom your contracts and certificates; the residual mix for everything else
Do certificates change it?NoYes

Companies with operations in markets that offer contractual instruments must report both figures, labelled by method. The GHG Protocol calls this dual reporting. Where no instruments exist, the location-based figure is used in both totals. Not having contractual data for every site does not make a report non-compliant.

The Scope 2 Quality Criteria

Every instrument used in the market-based method must meet these criteria. In summary, it must:

  1. Convey the emission rate of the electricity it represents.
  2. Be the only instrument carrying that claim for that electricity.
  3. Be tracked and redeemed, retired or cancelled by or on behalf of the reporting company.
  4. Be issued and redeemed as close as possible to the period of consumption.
  5. Come from the same market as the consumption it is applied to.

Three further criteria cover utility emission factors, direct purchases from generators and the residual mix:

  1. Utility-specific emission factors must be based on delivered electricity and account for certificates sold off.
  2. For direct purchases or on-site generation, all instruments for that electricity must go to the reporting company only.
  3. A residual mix must be available for the market, or its absence must be disclosed.

Residual mix

The residual mix is what is left of a grid's generation after all claimed certificates are removed. It is the emission factor for electricity you have not covered with contracts or certificates. Without it, renewable electricity could be counted twice: once by certificate buyers and again in the grid average used by everyone else. Where no residual mix exists, companies must say so, because it may lead to double counting.

Where certificates fit

The guidance ranks market-based data by precision, from certificates and contracts that carry them, through supplier emission rates, to the residual mix and finally grid averages. It states this is not a preference between instrument types. Unbundled certificates, bought separately from the electricity, are a recognised instrument as long as they meet the Quality Criteria.

What is changing

GHG Protocol

The GHG Protocol consulted on a revised Scope 2 standard from October 2025 to January 2026 and received nearly 1,100 responses. The main proposals were hourly matching for large organisations, a requirement that clean electricity be deliverable to where it is used, a legacy clause for existing contracts and exemptions for smaller users. Support for hourly matching and deliverability was low. Support for the exemptions and the legacy clause was broad.

In July 2026 the GHG Protocol asked for further work on several market-based approaches. The Scope 2 Guidance will be folded into a consolidated corporate standard developed with ISO, with a public consultation planned for the second quarter of 2027 and publication for the fourth quarter of 2028. Until then, the 2015 guidance applies.

Science Based Targets initiative

Under the current near-term criteria, a target to source 80% renewable electricity by 2025 and 100% by 2030 is an acceptable alternative to a Scope 2 reduction target. The Corporate Net-Zero Standard version 2.0, mandatory for new target submissions from 1 February 2028, replaces this with low-carbon electricity targets. Unbundled certificates still count under version 2.0, but only from plants commissioned or repowered in the previous 15 years, matched within deliverability regions. Existing contracts are grandfathered.

This guide summarises public standards for orientation. It is not accounting advice. Check the requirements that apply to your report with your framework's documentation or your assurance provider.

Sources

  1. GHG Protocol Scope 2 Guidance (2015)
  2. GHG Protocol: Scope 2 public consultation, summary of feedback (29 July 2026)
  3. GHG Protocol: standard development updates (29 July 2026)
  4. SBTi Corporate Near-Term Criteria, version 5.3.1 (April 2026)
  5. SBTi Corporate Net-Zero Standard, version 2.0 (June 2026)
  6. SBTi: The Corporate Net-Zero Standard version 2.0